Digital Realty switches on a dedicated 110 kV power line for its Frankfurt campus

Tuesday, November 17, 2026 · 5 min read

The 16 km underground connection took about 20 months to build and can carry up to 300 MVA, clearing a power constraint on a campus planned for 11 data centers and 200 MW.

Bullish$DLR

📊 Scorecard: our Bullish call on $DLR is scored from $178.77, the last close before it ran. Its first result comes after the next close.

Digital Realty switches on a dedicated 110 kV power line for its Frankfurt campus

The News

Digital Realty announced on November 17 that its dedicated 110 kV power connection to Digital Park Fechenheim in Frankfurt is now operational. The connection runs about 16 kilometres fully underground from the Karben substation to the campus, and it is designed to provide up to 300 MVA of grid connection capacity.

The connection is owned by Digital Realty itself. It took around 20 months to build and commission, and it represents a triple-digit million-euro investment — meaning more than 100 million euros — in a dedicated high-voltage backbone for the campus buildout.

At full build-out, the campus is planned to comprise 11 data centers with up to 200 megawatts of IT capacity. Three data centers are already in operation, and a fourth is scheduled to go live in 2027. This is a mid-cycle infrastructure milestone rather than a new deal: no customer or lease was attached to the announcement.

Power is the bottleneck for European datacenters, and this line removes it for one of Frankfurt's biggest campuses.

Why It Matters

In the datacenter business, power is the product. Customers rent space, cooling and electricity, and the electricity is the hard part: a single campus can use as much power as a small city. A 300 MVA connection is the kind of capacity that takes years to arrange, which is why Digital Realty started building it about 20 months ago and why finishing it matters now.

Frankfurt is one of Europe's largest datacenter markets — second only to London, per Cushman & Wakefield's EMEA Data Centre Update H1 2025 — and competition for power there is fierce. By building and owning its own high-voltage line, Digital Realty does not have to wait in line for grid upgrades or negotiate with the local utility for spare capacity. It controls the timeline for its own campus, and that is a real advantage when customers are choosing where to put their servers.

The story is modest because there is no customer attached — this is infrastructure, not a sale. But infrastructure is what makes sales possible. With the power backbone in place, the remaining eight buildings on the campus can be built and leased without the power question hanging over them, and that de-risks the whole 200-megawatt plan.

Analyst's Take

Our call is Bullish. This is a small story in dollars but a meaningful one in practice: a datacenter campus is only worth what its power connection can support, and Digital Realty just removed the constraint on a 200-megawatt European site. Three buildings are already running, a fourth arrives in 2027, and the power to support all 11 is now in place.

The investment also tells you how seriously the company takes Frankfurt. A triple-digit million-euro, 16-kilometre underground high-voltage line is not something you build on a whim; it is a bet that demand for capacity in one of Europe's biggest datacenter markets will keep growing. Owning the connection outright gives Digital Realty control over its own schedule instead of waiting on the local grid.

There is no new customer or lease here, so do not overread it. But for a landlord whose business is selling powered space, having the power ready before the buildings is exactly the right order. Reader poll: Bullish or bearish on $DLR? Vote: Bullish, Bearish, Mixed.

Are you bullish or bearish on this story?

By The Numbers

110 kVVoltage of the new dedicated connection
16 kmFully underground route from Karben substation
300 MVAGrid connection capacity
~20 monthsTime to build and commission
11Data centers planned at full build-out
200 MWPlanned IT capacity at full build-out

FAQ

What is 110 kV?

110 kV means 110,000 volts. It is a high-voltage power line of the kind that carries electricity from the main grid to a large site. Most homes run on a few hundred volts, so this is roughly 500 times more powerful.

What is MVA?

MVA stands for megavolt-amperes, a measure of how much electrical power a connection can carry. 300 MVA is roughly enough capacity for a small city's worth of datacenter equipment.

Why build a dedicated power line?

Datacenters use enormous amounts of electricity, and a shared local grid may not have enough spare capacity. A dedicated line guarantees the campus gets the power it needs, on its own schedule.

👁

Source: GlobeNewswire via TradingView