The News

TeraWulf reported third-quarter results on November 6, before the market opened, and the headline number needs a warning label. Total revenue was $76.2 million, up 51% from a year earlier and 70% higher than the $44.8 million of the second quarter, beating expectations of about $70.43 million. Earnings per share were a loss of $0.03, better than the $0.18 loss analysts expected. The shares rose 12.80% to $11.37 on the day — but they are still down 10.82% over five sessions.

The real story is the pivot. Revenue from leasing high-performance computing capacity — renting out datacenter space and power to AI customers — reached $63.0 million, or 83% of total revenue, up 97% from the previous quarter. That $63.0 million breaks down into $46.0 million of rent, $11.3 million of tenant fit-out revenue — money paid by customers to customise the space — and $5.4 million of power pass-through, where TeraWulf bills customers for the electricity they use. Bitcoin mining revenue, the old business, fell 69% from a year earlier to $13.2 million, from $43.4 million.

Now the warning label. TeraWulf reported GAAP net income of $709.9 million — but almost all of it is paper, not profit from running the business. It includes a $728.4 million non-cash gain from the rising value of warrants held by Google — warrants are rights to buy shares at a set price, and when TeraWulf's shares rise, those warrants become more valuable on paper — plus a $95 million gain on the sale of its 50.1% stake in the Abernathy joint venture, for total consideration of about $530 million ($250 million received in the quarter, $150 million due by December 31, 2026 and about $130 million due by April 30, 2027). Strip those out and the picture flips: the operating loss was $88.2 million and non-GAAP adjusted EBITDA — a measure of earnings before interest, tax, depreciation and amortisation, adjusted for one-offs — was negative $12.8 million. Cash, cash equivalents and restricted cash totalled about $2.4 billion at quarter-end, and net debt was about $0.7 billion.

Operationally, the build-out continues. Lake Mariner had 102 megawatts of revenue-generating critical IT capacity at September 30, with 336 megawatts under construction. The 20-year Anthropic lease at the Justified campus covers about 401 megawatts and about $19 billion of contracted revenue over the term — but the lease financing is anticipated, not yet completed. Muskie now has 1 gigawatt of contracted power after expanded service agreements with Kentucky Power and AEP.

HPC lease revenue reached $63.0 million — 83% of the total, up 97% quarter on quarter.

Why It Matters

TeraWulf is the clearest example of a Bitcoin miner reinventing itself as an AI landlord, and this quarter the reinvention crossed a line: leasing is now 83% of revenue, and it nearly doubled in a single quarter. That is a real business transformation, not a rebrand — customers are paying rent, paying for fit-outs and paying for power, and the $19 billion Anthropic contract is the kind of long-term commitment that can anchor a company for two decades.

But the quarter also shows why the market still discounts these companies. A $709.9 million headline profit that turns into an $88.2 million operating loss once you remove a paper gain is a reminder that the business itself still loses money, and the biggest contract in the company's history still needs its financing completed. If that financing lands, TeraWulf has a two-decade revenue stream. If it slips, the company is spending heavily to build capacity for a deal that is not yet fully funded.

Analyst's Take

Our call is Mixed, because both readings of this quarter are true at once. The demand side is genuinely strong: revenue beat expectations, leasing grew 97% in a quarter, and a 20-year, $19 billion contract with Anthropic is the kind of backlog most companies would envy. The profit side is genuinely weak: the business lost $88.2 million on operations and adjusted earnings were negative, so the headline profit is an accounting entry, not cash the company earned.

The shares rose 12.80% on the day, which tells you the market liked the revenue beat and the leasing growth more than it feared the operating loss. That is a reasonable reaction — but it is also a bet that the Anthropic financing gets done and that leasing keeps growing fast enough to cover the losses. Until the financing is signed, this is a story about a transformation that is working, funded by a deal that is not yet finished.

Are you bullish or bearish on this story?

By The Numbers

$76.2MTotal revenue, +51% year over year, beating ~$70.43M expected
83%Share of revenue from HPC leasing — $63.0M, up 97% quarter on quarter
$709.9MGAAP net income — almost all a $728.4M non-cash warrant gain
−$12.8MNon-GAAP adjusted EBITDA; operating loss was $88.2M
$19BContracted revenue, 20-year Anthropic lease (~401 MW)
+12.80%Shares, to $11.37 — still −10.82% over five days

FAQ

What is a warrant gain, in plain terms?

A warrant is a right to buy shares at a set price. Google holds warrants in TeraWulf, and when TeraWulf's shares rise, those warrants become more valuable — so accounting rules record a gain. No cash changes hands; it is a paper entry that can swing the reported profit by hundreds of millions.

What is adjusted EBITDA?

Earnings before interest, tax, depreciation and amortisation, with one-off items stripped out. It is meant to show how the underlying business is doing. TeraWulf's was negative $12.8 million, meaning the core business lost money in the quarter even though the headline profit was $709.9 million.

What is HPC leasing?

Renting out datacenter space, power and cooling to AI customers who need somewhere to run their computing. Instead of mining Bitcoin itself, TeraWulf leases its buildings and electricity to companies like Anthropic, which run their AI systems there.

Why does the Anthropic lease financing matter?

The 20-year lease promises about $19 billion of contracted revenue, but the financing to build the capacity is anticipated, not yet completed. Until it is signed, the revenue is a commitment on paper rather than a funded project.

What is a joint venture stake sale?

TeraWulf owned 50.1% of the Abernathy project with a partner and sold that stake for total consideration of about $530 million — $250 million received in the quarter, $150 million due by December 31, 2026 and about $130 million due by April 30, 2027. The company recognised a $95 million gain on the sale, which is part of why the reported profit looks so large — it is a one-off, not recurring income.

👁